Concept
A clear, build-ready plan you can take anywhere.
- Site analysis
- 2D site plan
- Concept moodboard
- 1 revision round
Service
Lived-in homes, brought back to life.
What's included
Deliverables
Three ways to start
Fixed-fee design tiers. Build cost is separate (typical range $40K–$250K+).
A clear, build-ready plan you can take anywhere.
The package most clients pick when they intend to build.
Full architectural integration with HOA-ready package.
Design fees only. Permits, HOA filing fees, materials, and construction quoted separately.
2026 pricing
Orange County renovation costs run $50 to $800+ per square foot depending on how deep the work goes. A cosmetic refresh that keeps every wall and system in place sits at the bottom; a full gut with new plumbing, electrical and an addition sits at the top.
Per-square-foot pricing only means something once you fix the house size. A $200 per square foot renovation on a 3,000 sq ft home is $600,000; the same rate on a 1,500 sq ft cottage is $300,000.
| Depth | Cost / sq ft | 3,000 sq ft home | What it covers |
|---|---|---|---|
| Cosmetic refresh | $50 – $150 | $150,000 – $450,000 | Paint, flooring, basic kitchen update, bathroom refresh. No walls moved. |
| Mid-level renovation | $150 – $300 | $450,000 – $900,000 | Some wall movement, premium finishes, custom cabinetry, updated systems. |
| Full gut to studs | $300 – $600+ | $900,000 – $1,800,000+ | New plumbing and electrical, luxury finishes throughout, structural changes. |
| Renovation plus addition | $400 – $800+ | $1,200,000 – $2,400,000+ | Square footage added; foundation, framing and roof tie-in. |
Room-by-room: kitchen remodels run $25,000–$75,000, bathroom renovations $15,000–$45,000, and whole-home remodels $150,000–$1,500,000+.
Schedule
A cosmetic refresh on a 3,000 sq ft home takes 8 to 12 weeks. A full gut takes 9 to 14 months once design, permitting and plan check are counted — and permitting is where most Orange County schedules actually slip, not construction.
| Phase | Cosmetic | Mid-level | Full gut |
|---|---|---|---|
| Design and documentation | 2 – 4 weeks | 6 – 10 weeks | 10 – 16 weeks |
| Permit and plan check | 0 – 3 weeks | 6 – 12 weeks | 10 – 20 weeks |
| Demolition | 3 – 5 days | 2 – 3 weeks | 3 – 4 weeks |
| Rough systems (plumbing, electrical, HVAC) | — | 3 – 5 weeks | 8 – 12 weeks |
| Finishes and cabinetry | 5 – 8 weeks | 10 – 16 weeks | 16 – 24 weeks |
| Total | 8 – 12 weeks | 6 – 9 months | 9 – 14 months |
Deeper cost and sequencing detail is in our Orange County whole home renovation guide.
FAQ
Home renovation costs in Orange County vary by scope: kitchen remodels typically run $25,000-$75,000, bathroom renovations $15,000-$45,000, and whole-home remodels $150,000-$1,500,000+. Costs depend on materials, layout changes, and finish level. We provide free in-home estimates with transparent, itemized pricing.
Kitchen remodels typically take 6-12 weeks, bathroom renovations 4-8 weeks, and whole-home remodels 3-8 months. Timelines depend on scope, permit requirements, material lead times, and structural changes. We provide a detailed project schedule during your consultation and keep you updated weekly.
Most renovation projects require permits, especially those involving structural changes, plumbing, electrical, or HVAC work. Cosmetic updates like painting and cabinet refacing typically do not. NHG HOME handles all permitting, HOA submissions, and inspections as part of our service at no extra hassle for you.
For kitchen and bathroom renovations, most homeowners stay in their homes. We set up dust barriers, protect finished areas, and maintain a clean worksite daily. For whole-home remodels involving structural work, temporary relocation may be more comfortable. We discuss living arrangements during planning to minimize disruption.
Yes. Layout-driven renovations often need structural changes (open-concept walls, larger openings, additions). We coordinate the structural engineer, pull the permit, and execute the work — same team, same schedule, no handoffs.
Yes. ADU construction is one of our renovation specialties — both garage conversions and new detached units. Orange County and most OC cities have adopted statewide ADU streamlining, so the permit path is faster than it used to be. We size, design, permit, and build.
During a cosmetic refresh, usually yes if the work is zoned room by room. During a full gut, no — water, power and often the roof come offline, and most Orange County jurisdictions will not sign off on occupancy mid-project. We plan the move-out window into the schedule so it is not a surprise at demo.
Plan check, almost always. Construction runs on a predictable rhythm; municipal review does not. A full gut can sit 10 to 20 weeks in permitting depending on the city and how complete the submittal is. We submit a complete set the first time because a resubmittal restarts the queue rather than resuming it.
Yes, with stamped engineering. Removing a bearing wall requires a calculated beam, a permit, and inspection at both rough and final. We include the engineer in the design phase so the beam depth is known before the ceiling design is finalized, which avoids the classic surprise of a soffit nobody planned for.
Three minutes of questions. We come back with a recommended scope, a budget range, and a date to walk the home.